- County Executive Aisha Braveboy signed an executive order suspending issuance of data center construction permits pending a task force review.
- Four council members introduced legislation to pause reviews and approvals for future data center projects, with some reports citing a November target for recommendations.
- Other reporting says the task force may not deliver proposed standards until later next year, leaving the duration of the pause uncertain.
- The Brightseat Tech Park proposal by Brightseat Associates, affiliated with Lerner Enterprises and the Tower Cos., holds entitlements for a roughly $5 billion, 4.1 million-square-foot campus projected to generate about $54 million in annual tax revenue.
- Leaders are reassessing a 2021 approval change that enabled planning-board signoffs without council review, and council members acknowledge the pause could face legal challenges from developers.