Overview
- Power Mech Projects will execute the balance-of-plant EPC package for the 1x800 MW Singareni Super Thermal Power Project, Stage II, in Mancherial, Telangana, for a value stated as over Rs 2,500 crore excluding GST.
- Published reports differ on the schedule, with one citing a 36-month timeline from commencement and another citing 38 months from the start of work.
- The scope covers end-to-end responsibilities from design and engineering through civil and structural works, erection, testing, commissioning, trial run, handover, and annual maintenance until handover.
- Shares rose intraday on the announcement, with outlets reporting gains ranging from about 2.7% to 5.3%, including a move to roughly Rs 2,973.
- Context from recent filings shows FY25 revenue of Rs 5,279 crore and 165 ongoing projects, making the new order a material addition to near-term workload.