The UK government and Tata Steel agree on a £1.25 billion investment plan, but 2,500 jobs will be lost in the process.

  • The UK government will contribute £500 million towards the construction of an electric arc furnace at the Port Talbot plant.
  • Tata Steel will invest £750 million in the project, aimed at reducing carbon emissions and modernizing production.
  • The transition will lead to the loss of 2,500 jobs, despite improved redundancy and reskilling packages for affected workers.
  • The new electric arc furnace is expected to be operational by 2027, significantly reducing the plant's carbon footprint.
  • Unions have expressed mixed feelings, acknowledging improvements in the deal but lamenting the job losses.