PMC Injects Rs 470 Crore to Unlock Katraj–Kondhwa Widening, Targets December 2026

The civic body shifted to self-funding to break years of delays caused by land acquisition disputes.

Overview

  • The allocation has been credited to the district collector’s treasury to speed up land purchases for the corridor.
  • The design has been pared back to a 50-metre width from the earlier 84 metres to reduce cost and shorten timelines.
  • About half of the roughly 94,000 square metres required is acquired, with remaining owners seeking cash instead of TDR in many cases.
  • Construction is advancing on acquired sections, including grade separators and two 300mm rainwater lines at known flooding spots near Rajas Society and the SBI branch.
  • The project is under PMC’s ‘war room’ monitoring, following earlier support of Rs 140 crore from the state and Rs 200 crore from PMC prior to this fresh push.