Piura’s Miguel Grau Stadium Contract Terminated as Oversight Cites Failures Across Two Projects

Auditors say unanswered technical queries left the remodel frozen with progress near 1.6%.

Overview

  • Consorcio EPiura notified the Piura regional government on December 15 that it was resolving Contract No. 065-2025-GRP, invoking supervening events under procurement rules.
  • A physical inspection and inventory were scheduled for December 19 at the stadium, with a committee of engineers appointed by the Dirección General de Construcción to document the site.
  • Work has been halted since November 3 after Queries No. 48 and 50 on topography and structural foundations went unanswered beyond the five-day legal deadline, leading to a formal suspension recorded on November 18.
  • A Contraloría control milestone report on November 27 found executed progress of 1.64% versus 17.66% programmed as of November 26, warning that delayed query responses jeopardized contractual goals.
  • The Regional Council’s special commission also reported information gaps in Sullana’s Campeones del 36 technical-file reformulation, noting the subregional office only cited a 10% retention without detailing actual progress.