Phoenix Open Begins Rebuild of Iconic 16th Hole With Four-Story, Reusable Arena for 2026

Organizers say a reusable modular build will cut construction materials to reinforce the tournament’s zero-waste identity.

Overview

  • Construction is underway with a four- to five-month build targeting substantial completion by January 2026 followed by about 30 days of final preparations.
  • The redesigned venue expands to four stories and features wider bays, higher ceilings, fewer support columns and frameless glass for clearer sightlines.
  • A new Pin Hi Club next to the green will debut with daily individual hospitality tickets, LED video boards and upgraded interior amenities.
  • Tournament leaders emphasize a 100% reusable, modular structure intended to reduce metal, wood and scrim through the event’s zero-waste program.
  • Officials say the arena will accommodate about 17,000 fans per day, and the traditional grandstand seating will remain available.