Overview
- The post-construction control was initiated during on-site inspections on December 30–31 after the contractor ended the S/192 million rehabilitation contract.
- Only 1.64% physical progress was recorded since work began on June 12, 2025, despite disbursements exceeding S/3 million.
- Consorcio EPiura cited obstacles tied to deficiencies in the technical dossier as its reason for resolving the agreement with the regional government.
- Auditors will determine possible administrative, civil or criminal liabilities and examine failures in project formulation identified as recurrent in Piura.
- The comptroller also reviewed other stalled investments, including a hospital with a SIS debt over S/86 million, while the regional governor said he hopes to restart stadium works in early 2026.