Peru's Comptroller Launches Audit Into Halted Miguel Grau Stadium Works in Piura

The review seeks to confirm planning deficiencies that led to the contract’s termination to establish responsibility.

Overview

  • The post-construction control was initiated during on-site inspections on December 30–31 after the contractor ended the S/192 million rehabilitation contract.
  • Only 1.64% physical progress was recorded since work began on June 12, 2025, despite disbursements exceeding S/3 million.
  • Consorcio EPiura cited obstacles tied to deficiencies in the technical dossier as its reason for resolving the agreement with the regional government.
  • Auditors will determine possible administrative, civil or criminal liabilities and examine failures in project formulation identified as recurrent in Piura.
  • The comptroller also reviewed other stalled investments, including a hospital with a SIS debt over S/86 million, while the regional governor said he hopes to restart stadium works in early 2026.