- Contraloría’s Control Milestone Report N° 077-2025-OCI/5349-SCC documented defects during inspections from August 1 to September 26, 2025.
- Auditors found no required expansion joint between rainwater concrete gutters and the existing perimeter wall after concrete was poured without the specified separation.
- Inspectors observed longitudinal and transverse cracking and premature surface wear (scaling) in the slab of the roofed courtyard, risking reduced service life.
- Safety measures were only partially implemented despite on-site specialists in occupational safety, health, and environment, exposing workers and opening the door to contractual penalties.
- The S/36,111,254 contract, awarded in April 2024, now targets completion on January 1, 2026, and the report has been published and notified to the Piura regional governor with calls for immediate fixes.