Overview
- Transport Minister César Sandoval said the government will provide technical accompaniment to align the municipal proposal with national standards.
- The plan envisions two unidirectional tunnels totaling 19.4 kilometers, to be built using the Austrian method (NATM) with an estimated cost of S/3,607 million.
- Authorities estimate a 60‑month execution window once approvals are in place, with dossier preparation and profiling identified as the immediate tasks.
- The initiative remains preliminary without a definitive study or secured financing, and execution cannot begin until those requirements are met.
- Officials project benefits for about 1 million residents in east Lima, including a significant reduction in traffic between La Molina and Surco.