Overview
- Kelly Drive will close nightly from 8 p.m. to 6 a.m. on weeknights between August 4 and August 29 for milling and paving.
- Work is split into two sections: Ridge Avenue to Fountain Green Drive and Reservoir Drive/Strawberry Mansion Drive to 25th Street.
- Southbound traffic on the first section will detour via Ridge Avenue, 33rd Street, Diamond Drive and Fountain Green Drive; the second section will reroute via Strawberry Mansion Drive, Girard Avenue, 29th Street, Pennsylvania Avenue and 25th Street.
- The schedule is weather-dependent and PennDOT advises motorists to allow extra travel time for significant backups.
- Daytime closures for inlet and manhole repairs will begin in early September, with final paving slated for mid to late September if weather permits.