Pemex, Japan Advance Energy-Efficiency Project at Cadereyta Refinery

The effort now focuses on validating efficiency gains before releasing quantified results.

Overview

  • Advanced Process Control is being implemented on direct-fired heaters in the primary and vacuum distillation Combined 1 unit.
  • The program targets lower greenhouse-gas emissions and energy savings by strengthening the refinery’s Distributed Control System.
  • Current work centers on system integration, operational validation, and evaluation of improvements in energy consumption.
  • Completed steps include rehabilitating the Combined 1 unit, modernizing heaters, and installing oxygen analyzers to improve combustion efficiency.
  • The collaboration, formalized in 2023, includes JICA sponsorship with technical participation from Adaptex and received public backing from Pemex leadership during a December technical visit.