Particle.news
Download on the App Store

Parel Residents Halt Elphinstone Bridge Piling Over Vibration Fears as VJTI Steps In

Work is set to restart under monitored conditions following a joint site inspection by VJTI with MMRDA officials.

Overview

  • About 50 residents intervened at pier locations P61 and P61A, stopping work after seven piles were completed near century-old chawls.
  • VJTI installed accelerometers, crack gauges and tilt sensors and advised lower rig RPM, quieter mud removal and continuous vibration tracking.
  • MMRDA officials said construction will resume under close supervision to protect surrounding buildings during piling.
  • Residents plan to meet MMRDA for safety assurances and clarity on rehabilitation after a redesign reduced planned demolitions from 19 buildings to two.
  • Western Railway is expected to approve MRIDC’s dismantling of the span over the tracks next week as debris clearing from the approaches enables crane deployment.