Overview
- A deflagration on March 1 at kilometer KP 43 in Megantoni, Cusco, stopped Camisea gas and liquid gas transport and disrupted supply for about two weeks.
- Osinergmin says its technical investigation is essentially complete but cannot run specialised laboratory tests on metallic pipe samples that have been immobilized in Lurín since March 26.
- The regulator already issued three reports finding that Transportadora de Gas Natural did not prove force majeure and that contractual duties to guarantee flow and pressure from March 1–13 were not met.
- Because the Public Ministry has not ordered the pending diligences, Osinergmin has asked the Presidencia del Consejo de Ministros, the Ministry of Energy and Mines and the Defensoría del Pueblo to urge the Fiscalía to act.
- If tests are delayed further, Osinergmin cannot formally close the probe or impose administrative measures, leaving both accountability and potential sector responses to supply risk unresolved.