The plan directs about €3 billion to expand France-based hosting capacity for cloud and AI under a jointly controlled platform.

The logo of French telecom operator Orange is seen during the Viva Technology conference dedicated to innovation and startups at Porte de Versailles exhibition center in Paris, France, June 12, 2025. REUTERS/Benoit Tessier

Overview

  • Orange and global infrastructure investor Morrison have signed an exclusivity agreement to form a 50/50 jointly controlled data centre company located in France.
  • Under the proposal Orange would contribute five major data centres across four campuses in Chevilly-Larue, Aubervilliers, Chartres and Val-de-Reuil to the new platform.
  • The platform is targeting roughly 400 MW of total capacity and would be supported by a €3 billion investment programme combining Orange assets, Morrison equity and debt.
  • Orange would keep operational control over areas used for its own services and Orange Business is expected to be the exclusive distributor of the joint venture’s colocation and hosting offers.
  • The deal remains conditional on employee representative consultations and regulatory approvals with signing planned by the end of 2026 and closing anticipated in the first quarter of 2027.