Particle.news

Download on the App Store

OpenAI’s Stargate Adds Five U.S. Sites, Nears 7 GW With Over $400 Billion Committed

New GPU commitments with creative financing aim to meet surging AI compute demand.

Overview

  • OpenAI, Oracle and SoftBank named new data center locations in Shackelford County and Milam County, Texas; Doña Ana County, New Mexico; Lordstown, Ohio; and an undisclosed Midwest site.
  • The Abilene, Texas flagship is partly operational on Oracle Cloud Infrastructure with Nvidia GB200 systems, targeting roughly 900 megawatts across eight buildings as construction continues.
  • Combined plans now total nearly 7 gigawatts of capacity and more than $400 billion in investment commitments over three years, with the venture still targeting 10 gigawatts and $500 billion by year-end.
  • Nvidia agreed to invest up to $100 billion and supply GPUs, with OpenAI signaling leasing arrangements, initial $10 billion in cash from Nvidia, and potential debt financing to secure chip inventory and accelerate builds.
  • The expanded buildout creates about 25,000 onsite jobs and marks a diversification of OpenAI’s compute partnerships beyond Microsoft, even as experts and residents flag power, emissions and water impacts at host communities.