Overview
- The open house ran from 5 to 7 p.m. at Trollwood in Moorhead, with staff from Fargo, Moorhead and Houston Engineering on hand to answer questions.
- The proposed span would link 40th Avenue South in Fargo to 50th Avenue South in Moorhead near the Bluestem Amphitheater, connecting existing shared-use paths.
- City engineers estimate the project will cost a little over $7 million.
- The timeline outlined calls for construction to begin in spring 2027 with completion targeted around mid-2028.
- Officials emphasized that aesthetic elements remain flexible, and written comments are being accepted through Nov. 13 to Houston Engineering under project SP 144-09-020.