Overview
- The Land Transport Authority announced on Sept 17 that the North‑South Corridor will open in phases two years later than planned, with viaduct sections from 2029 and tunnel sections from 2031.
- At Novena the corridor’s southbound tunnel is complete but the stacked northbound tunnel hit fractured rock and groundwater, so crews switched to slower, phased mining with grouting, support installation and controlled blasting for the lower half.
- Site investigations at Thomson, Gambas Avenue and Woodlands found harder and higher rock levels that required deeper piling, longer diaphragm‑wall construction and excavation of large rock volumes.
- LTA said roads, footpaths and interim cycling and pedestrian facilities will be progressively reinstated from 2028, with more technically difficult stretches cleared from 2030 as structural works finish.
- Final cost and contractual outcomes remain unresolved because contractors can claim for differing ground conditions, and residents and businesses along the route face continued disruption to trade and travel until works finish.