Overview
- Work halted for months after a deep foundation design error will restart on the current site using a micropile fix.
- Design firm SMRT will pay the state $9.9 million without admitting wrongdoing, and the settlement assigns no responsibility.
- Officials estimate up to $5 million in additional delay-related expenses that taxpayers may need to cover.
- The new completion target is October 2027, putting the 24-bed forensic facility roughly a year behind schedule.
- Executive councilors criticized the limited recovery, while the attorney general argued a lawsuit could have added years of delay.