- The Southern Bench of the National Green Tribunal, ruling Thursday, dismissed the BRS leader’s challenge at the admission stage as premature because his concerns are covered by the project’s Terms of Reference.
- Telangana’s counsel said an application for environmental clearance is underway and any current activity follows the ToR that guides the project’s environmental impact study.
- BRS leader P. Karthik Reddy said the case was only disposed of after the State explained the project is at the application stage, and he claimed the government told the bench it would not proceed without required permissions.
- Karthik Reddy warned he will return to the tribunal if those assurances are not kept, while some reports quoted officials saying the decision lets the government move ahead with planned phases.
- The Musi rejuvenation plan targets sewage treatment, stronger flood control, and new public spaces along the river, changes that could improve water quality and reduce inundation risks for neighborhoods near the corridor.