New Jersey Offshore Wind Project Faces Significant Delays

Leading Light Wind requests pause due to turbine supplier issues, reflecting broader industry challenges.

  • Leading Light Wind has asked the New Jersey Board of Public Utilities for a pause until December 20 to secure a new turbine blade supplier.
  • The project has lost key suppliers, including GE Vernova and Siemens Gamesa, causing significant disruptions.
  • New Jersey has become a focal point for opposition to offshore wind, with environmental and financial concerns raised.
  • Previous offshore wind projects in New Jersey, such as those by Ørsted, have also faced financial infeasibility and cancellations.
  • Supporters argue that offshore wind is crucial for reducing fossil fuel dependence, despite the current setbacks.