Particle.news

Namma Metro Blue Line Begins Mainline Trial Runs

Outstanding signalling work and a small amount of track and station finishing will decide when passenger services start.

Overview

  • Trial runs on the 58.19 km Blue Line began in early November, with trains moved from Byappanahalli toward KR Puram and Doddanekundi as BMRCL expands mainline testing.
  • BMRCL has been energising traction systems since late October, progressively powering 33 kV cables and the third rail between Baiyappanahalli and Marathahalli to support integrated runs.
  • Signalling integration remains the key technical hurdle and about 2 km of track work plus finishing at some stations still need completion before kinematic testing and safety approvals.
  • Officials are keeping a phased opening timetable, with Phase 2A (Central Silk Board–KR Puram) targeted for mid‑2027 and the full airport link currently aimed for around March 2028.
  • The line will use driverless‑capable, luggage‑friendly trains, link major IT hubs along the Outer Ring Road to Kempegowda International Airport, and is expected to boost local commercial and rental demand.