Overview
- In a July 8 review, Chief Minister Naidu obtained specific start and finish dates from all 72 land-allotted institutions, with ten already breaking ground and three buildings completed.
- Institutions committed to phased construction starts: three this month, 15 within two months, 13 within five months and 17 within six months.
- The Capital Region Development Authority has allocated roughly 948 acres to academic, corporate, government and hotel entities as part of the city’s expansion.
- Several allottees requested additional land for convention centres, parking facilities and a postal training centre for Andhra Pradesh and Telangana staff.
- The administration aims to complete Amaravati within three years, positioning it as a green-blue, zero-emission AI and Quantum Valley financial and innovation hub.