- The Bangalore Development Authority’s Nagavara-to-Hebbal flyover loop is nearly complete and slated to open before August 15
- The loop forms one half of a dual-ramp system designed to separate airport-bound traffic by linking Tumakuru Road, Outer Ring Road, Nagavara and KR Puram corridors
- Crews have dismantled two spans over the KR Puram section during final works, temporarily narrowing lanes and sustaining peak-hour delays of up to 30 minutes
- Metro construction barricades between Manyata Tech Park and Kalyan Nagar continue to cause severe morning jams, complicating traffic flow around the interchange
- The project missed earlier April and May deadlines due to heavy vehicular movement and required inter-agency approvals, including Railway clearance for composite steel girders