Munich Service Back Online After Dual Cable Faults, Secondary Repair Underway

Crews are finalizing repairs on the second cable fault after emergency measures restored power to 5,700 homes in eastern Munich.

Image
Image
Image
Image

Overview

  • A cable ring in eastern Munich experienced two nearly simultaneous faults around 17:50 on July 16, cutting power to approximately 5,700 households.
  • Stadtwerke München dispatched its security service to isolate the faults and used network switching and emergency generators to restore most customers within three hours.
  • The first cable fault has been fully repaired, and work on the second fault continues without impacting the current power supply.
  • Tuesday’s substation failure in Bamberg left over 10,000 homes without electricity and highlights recurring weaknesses in Bavaria’s aging distribution network.
  • Stadtwerke München maintains round-the-clock monitoring and has accelerated infrastructure assessments to prevent future outages.