- Construction has started on Rheinstraße in Schwabing, focusing on improving traffic safety and school routes near Simmernstraße schools.
- The redesign includes 2.30–2.50 m wide bike lanes, 2.50–3 m sidewalks, and safety separators to separate cyclists and pedestrians from vehicles.
- Parking spaces on the north side are being removed, with 25 spaces retained on the south side, nine designated for daytime deliveries.
- Plans call for 22 new trees, 32 bike parking spaces, and the addition of an express bus line with a new stop near Leopoldstraße.
- The project is on track for completion, with main street works set to finish by the end of 2025 and final tasks by May 2026.