Overview
- The €665 million project will boost Terminal 1’s capacity by six million passengers annually, matching Hannover Airport’s yearly throughput.
- Three double-deck A380 passenger bridges are being installed to support growing intercontinental flight operations.
- Early technical tests have begun on security scanners and boarding systems, with a full ORAT simulation planned for October 2025 involving up to 1,000 trial passengers.
- Cathay Pacific will commence flights from the new terminal on June 26, 2025, joining carriers such as Etihad, Delta and Emirates.
- Pandemic-related delays and rising material costs pushed the original sub-€500 million budget to its current estimate of €665 million.