Overview
- The BMC will suspend water supply to Mulund’s T ward from 10 am on August 21 to 4 am on August 22 to realign a 1,200 mm transmission main ahead of bridge piling.
- The pipeline diversion is intended to protect the main from damage during construction of a key bridge for the Rs 6,500-crore Goregaon–Mulund Link Road.
- Affected zones include stretches along the Goregaon–Mulund Link Road, Lal Bahadur Shastri Marg, Jawaharlal Nehru Marg, Devidayal Marg, Nahur Gaon and surrounding areas.
- Authorities have urged residents to stock sufficient water in advance and to boil or filter tap supply for up to five days after service is restored.
- This realignment is one element of broader utility shifts supporting GMLR’s tunneling and bridge works, with further planned disruptions likely as the project advances.