Overview
- Official photos released by the Mumbai Metro-3 account show the finished underground Girgaon station and describe it as the area’s first connection to the city’s rail network.
- Girgaon sits on the Worli–Cuffe Parade segment whose inauguration would make the Colaba–Bandra–SEEPZ Aqua Line fully operational.
- A site visit reported by Mid-day found most stations on the final stretch largely ready, with last clean-up and fit-out work under way at several entrances.
- At Girgaon, two of three entry and exit points appeared ready as workers cleared debris and completed final touches.
- Engineers built the station alongside century-old buildings in a tightly packed neighborhood, a task highlighted by reports as a careful, heritage-sensitive effort.