Overview
- The BMC has concretised 1,385 of 2,121 roads spanning 342.74 km, achieving 49.07 per cent of the 698.44-km target as of May 31, 2025.
- In Phase I, 582 of 700 roads covering 203.36 km have been completed, representing 63.53 per cent progress toward the December 2025 deadline.
- Phase II has seen 803 of 1,421 roads concretised across 139.38 km, marking 36.84 per cent of work ahead of its May 2027 conclusion.
- IIT Bombay serves as an independent third-party auditor to verify material and workmanship standards across the Rs 17,700-crore project.
- Barricades have been cleared and roads opened to traffic, with the BMC prohibiting any further excavations on concretised surfaces.