- Railway Minister Ashwini Vaishnaw confirmed that 76% of excavation work at the underground Bandra Kurla Complex (BKC) station has been completed.
- The B3 basement level and station wall strengthening at the BKC station have been finalized, marking a significant engineering milestone.
- A multi-storey underground station design is underway, with levels B1 to B3 designated for passenger services, operations, and train parking.
- Tunnel construction at Shil Phata and other land-acquired sections in Maharashtra is progressing rapidly.
- The Rs 1.08 lakh crore Mumbai-Ahmedabad High-Speed Rail project, funded by the Indian government, state governments, and a Japanese loan, remains on schedule for a 2028 operational launch.