MPCB Halts Adani Excavation at Sawarghar Over Missing Permissions

Regulators say work on two Sawarghar plots lacked required consents, prompting a board review with possible legal action.

Overview

  • The Maharashtra Pollution Control Board issued a stop-work notice on Nov. 20 that ordered Adani Renewable Energy One Ltd to halt excavation and construction at Gat Nos. 33 and 34 in Sawarghar village.
  • MPCB inspectors reported they found land being levelled for a temporary labour camp and material storage at those two plots without the mandatory consent or fresh environmental clearance for those parcels.
  • The Satara forest division had already served a show-cause/stop-work notice on Nov. 13 alleging work began without National Board for Wildlife permission, and Adani says its permanent project components hold statutory clearances.
  • MPCB invoked Section 33A of the Water Act and Section 31A of the Air Act in its directions, warned of legal action if work resumes without approval, and confirmed a follow-up visit found the order being followed.
  • The 1,500 MW Tarali pumped storage project is planned on roughly 150.7 hectares near eco-sensitive areas, so the dispute over temporary use of privately bought Sawarghar plots could delay construction, trigger formal probes, and affect how wildlife and pollution rules apply to support sites.