Overview
- Traffic is halted from 9:00 to 16:00 between Calle del Trabajo and Calle Eduardo Ruiz as crews work at the Plaza del Carmen crossing.
- The intervention removes damaged asphalt, stabilizes the base and installs hydraulic concrete to restore the carriageway.
- Officials plan to complete the operation the same day, contingent on weather conditions.
- Two crews are deployed with eight machines, four trucks and 25 workers, supported by an outlay of roughly 250,000 to 300,000 pesos.
- Authorities expect the deformation to recur at this vulnerable Centro Histórico site, so the area will be monitored and lanes reopened progressively as work allows.