Overview
- State officials report 48% overall progress, with electromechanical fabrication finished for stations 1–4 and at 88% and 85% for stations 5 and 6.
- Cabin production stands at 82% for the northern route and 77% for the southern route, and the first units have begun to arrive.
- Seven of the 33 initial towers have been installed, and authorities have identified 34 posts to the Benito Juárez zoo for the first phase of the line.
- Residents on Amadeo Betancourt near Ciudad Universitaria complain of dust, lost sales and an alleged injury, and a small group posted signs to press for mitigation.
- The city says the work there had neighborhood anuencia, Cabildo approval and required permits, notes one amparo in process over a post, and adds that documentation for the planned Santa María phase remains under review.