Overview
- Construction will run from 21:00 to 05:00 in required areas to avoid daytime traffic, the urban development secretary said.
- Starting Friday at 07:00, Jesús Solórzano Dávalos carries two-way local traffic between Avenida Madero Poniente and Nicolás de los Palacios Rubios.
- Guardia Civil and Policía Morelia implemented alternate routes by the monument to relieve Madero at Josefa Ortiz de Domínguez, where circulation is partial for Station 4 works.
- Officials cited more than 10,000 vehicles per day at the Station 4 area as a reason to shift heavy work to nighttime.
- Authorities report overall construction progress at 41.08% and expect the tower installation at that location to finish by late October.