MoEF&CC Grants Final Forest Clearance for Goregaon-Mulund Link Road Twin Tunnels

It authorizes BMC to begin compensatory planting in Chandrapur followed by tunnel boring preparations beneath Sanjay Gandhi National Park

Image
The ministry has directed the SGNP authorities to hand over 19.43 hectares of reserve forest land required for the tunnels to the Brihanmumbai Municipal Corporation
Image
Image

Overview

  • The Union environment ministry issued Stage II approval under Section 2 of the Forest (Conservation) Act for diversion of 19.43 hectares of SGNP forest land to the BMC
  • Each tunnel will span 4.7 km in length and 45.7 m in width at depths ranging from 20 to 160 m with cross-passages every 300 m
  • Legal safeguards ensure the forest retains its status and no surface trees will be impacted as the tunnels run entirely underground
  • As a mitigation condition, BMC must carry out 19.5 hectares of compensatory afforestation in Chandrapur district covering Vasanvihira and Gondamohadi villages
  • The ₹6,548 crore tunneling phase is part of the ₹14,000 crore, four-phase GMLR project that aims to cut Goregaon–Mulund travel from 75 to 25 minutes by October 2028