Modi to Review MumbaiAhmedabad Bullet Train Works at Surat Station on Nov. 15

Project officials report 326 km of viaduct completed on the 508‑km line, with the SuratBilimora stretch nearing readiness.

Overview

  • The Prime Minister is scheduled to inspect the under-construction Surat high-speed rail station around 10 a.m., according to the PMO.
  • Progress reported includes about 85% of the route on viaducts, 326 km of viaduct built, and 17 of 25 river bridges completed, with tunnel excavation advancing in Palghar.
  • The approximately 47 km SuratBilimora section has civil structures and track-bed laying fully completed, project authorities say.
  • Once operational, trains are expected to cut MumbaiAhmedabad travel time to roughly two hours (about 127 minutes), with phased openings previously outlined for 2027 through 2029.
  • The Rs 1.08 lakh crore project is largely financed by JICA loans (about 81%), with the remainder from Indian central and state equity, and cumulative spending was reported at Rs 78,839 crore as of June 30, 2025.