Modi Reviews Surat Bullet Train Station as MumbaiAhmedabad Project Marks Key Build-Out

Officials maintain a phased opening from 2027 to 2029 under a JICA-backed financing plan.

Overview

  • On Nov. 15, the prime minister inspected the under-construction Antroli station in Surat and reviewed progress with project officials.
  • NHSRCL reports more than 326 km of viaduct completed across the 508-km corridor along with 17 river bridges.
  • The 47-km SuratBilimora stretch is in an advanced state, with civil works and track-bed laid, and project sources indicate trial runs are being planned.
  • Railway Minister Ashwini Vaishnaw has set a staged commissioning: SuratBilimora in 2027, to Thane in 2028, and full Mumbai reach in 2029.
  • The Rs 1.08 lakh crore scheme is largely funded by JICA loans and is designed to cut MumbaiAhmedabad travel to about two hours.