Modi Reviews MumbaiAhmedabad Bullet Train Progress, Told Work Is Advancing Smoothly

The visit spotlighted a push to document methods in a 'Blue Book' to guide future high‑speed rail builds.

Overview

  • During a 15 November visit to the under‑construction Surat station, the Prime Minister reviewed progress and sought assurance on meeting speed and timetable targets, with the PMO issuing its update on 16 November.
  • Officials reported completion of 326 km of viaducts and 17 of 25 river bridges on the corridor.
  • The 508 km line spans 352 km in Gujarat and Dadra & Nagar Haveli and 156 km in Maharashtra, with roughly 85% of the route designed on viaducts.
  • On‑site teams highlighted advanced practices including robotic units welding rebar cages at the Navsari Noise Barrier Factory.
  • Modi urged the team to compile a lessons‑learned 'Blue Book' to enable replication of successful approaches and reduce repeated experimentation, with the project expected to cut MumbaiAhmedabad travel to nearly two hours.