Overview
- MMRDA, which on Tuesday shared a fresh update, said work is complete at 143 of 176 foundations and 141 piers along the corridor.
- It also reported 88 pier caps installed and 653 of 830 precast girders finished, marking steady superstructure gains.
- The project is a 7.35‑km, six‑lane elevated link between Atal Setu (the Mumbai Trans Harbour Link sea bridge) and the Mumbai–Pune Expressway via Chirle and Palaspe, designed to remove traffic signals.
- At Palaspe near Panvel, crews are widening slip and service roads to improve traffic flow and prepare seamless tie‑ins to the expressway network.
- MMRDA is holding to a February 2027 opening date, framing the link to speed trips to the Navi Mumbai International Airport and reduce delays for regular Mumbai–Pune travel.