Mitre Line Prepares for Month-Long Service Disruptions for Track Upgrades

Trenes Argentinos announces phased interruptions starting May 1 to modernize critical rail infrastructure and improve service efficiency.

Cuándo deja de funcionar el tren Mitre y por cuánto tiempo
Urgente: trenes con servicio limitado este fin de semana largo, ¿cuáles no llegarán a destino?
Los servicios del Tren Mitre se verán afectados todo mayo por obras (Gentileza Argentina.gob.ar).
Image

Overview

  • Night-time works are currently underway on the Tigre branch, altering first and last train schedules through April 30.
  • From May 1 to May 4, the Tigre branch will be fully suspended, while Bartolomé Mitre and José León Suárez branches will only operate to Belgrano R station.
  • Between May 5 and June 1, Tigre branch service will be limited to the Retiro-Victoria segment as track renewal continues.
  • The project will replace approximately 3 kilometers of aging rails in Olivos and San Fernando, including Carupá station, under the Emergency Ferroviaria initiative.
  • Trenes Argentinos aims to accelerate completion by working on two sections simultaneously, reducing execution time by two-thirds.