Overview
- Trenes Argentinos has scheduled a full interruption of the Mitre ramal Tigre for Saturday 21, Sunday 22 and Monday 23 November 2026 to allow concentrated replacement of track links at the access to Martínez and Tigre.
- During the same three days the José León Suárez and Bartolomé Mitre branches will run only limited services between Belgrano R and their terminals so crews can work without nightly time limits.
- The Sarmiento line will operate only between Once and Castelar from 14:00 on Saturday 21 until the last service on Monday 23 November while teams renew signaling circuits between San Antonio de Padua and Ituzaingó, with normal service planned for Tuesday 24.
- Trenes Argentinos reports measurable progress on the Mitre Tigre works — about 36 km of track and 42 of 47 km of third rail already replaced — but says remaining tasks include another 40 km of track re‑adjustment, full third‑rail replacement and fixes to level crossings, bridges and drains.
- Passengers should plan alternate travel for the affected segments because some sections still force precautionary speeds and the concentrated daytime works are needed to fully restore safety and reliability.