Overview
- Tender notices for rolling stock for Phase 1 trains have been issued on ComprasMX, marking the start of procurement for the network’s four routes.
- Construction of the Querétaro–Irapuato and Saltillo–Nuevo Laredo segments has been delayed from July to September 2025 due to extended bidding processes.
- The AIFA–Pachuca airport link is 90% complete after resolving neighborhood rights-of-way disputes and is scheduled to open by December 2025.
- The federal rail regulator ARTF is set to be renamed ATTRAPI and project delivery will be coordinated by SICT alongside Military Engineers.