Overview
- Officials said the low‑cost suburban service El Tehuanito will open in December with two weekday routes over 189 km, and stations are 82.6% complete.
- Line K from Ixtepec to Ciudad Hidalgo is about 87.7% built, with completion targeted for June 2026 and coordination under way to extend the link into Guatemala.
- The government reported core rail, port and logistics works are between 55% and 99% complete, with overall CIIT completion projected for March 2027.
- The Roberto Ayala–Dos Bocas connection to move output from the Olmeca refinery is progressing on right‑of‑way and is now slated to finish in March 2027.
- Operational Lines Z and FA have carried 134,903 passengers and 889,920 tonnes of cargo, and 14 development poles are advancing with nine concessioned and others in adjudication or declaratory stages.
 
 