Particle.news

Download on the App Store

Mexico CityAIFA Train Targets December 2025 Opening as Track Connection Work Begins

Short service adjustments mark the next step to link the Lechería branch with the Suburban Rail network.

Overview

  • President Claudia Sheinbaum said she expects to inaugurate the Lechería–AIFA extension in December 2025 after resolving local social conflicts that had delayed work.
  • The route is being built with a diversion to allow direct through-service to Pachuca, extending the corridor beyond the airport.
  • Ferrocarriles Suburbanos announced service impacts on August 22–23 for track tie-in works on the AIFA branch and will run double trains to boost capacity.
  • Official records cite about 23 km of double electrified track with six stations, a maneuver yard, pedestrian and vehicular bridges, and an initial fleet of 10 trains, with progress reported at roughly 80% as of March.
  • Sheinbaum highlighted AIFA’s growing airline offerings ahead of the 2026 World Cup and praised its management under General Isidoro Pastor.