Overview
- The cavity at Calle 4 and Avenida 5 measures roughly 10 meters across and 8 meters deep, and it swallowed a soda delivery truck 12 days ago.
- Crews finished the protective ademe and are repairing the large drainage line while installing fiberglass‑ and polymer‑coated reinforcement sections.
- Workers are dewatering the collector to assess its condition and determine the scope of replacement or repair for the damaged segment.
- Flow is slated to be diverted through Eje 6 and a collector box two blocks ahead to relieve pressure on the affected pipe.