Overview
- The nightly programmed effort deploys 50 crews to fix 10 kilometers of primary avenues per night through December, targeting roughly 1,000 kilometers.
- A separate 50-crew rapid-response operation will resolve citizen reports and emergencies within 48 hours via *0311 (LOCATEL) and a WhatsApp chatbot, Bachetel, launching next week.
- The repaving phase will cover 250 linear kilometers—about 4.1 million square meters—scheduled from October 2025 to May 2026 with staggered tenders and quality controls.
- Work prioritizes the 217 primary roads under city authority, coordinated by SOBSE and the SSC for night closures, calendars, and public notices, while alcaldías handle secondary streets with city support in emergencies.
- Officials reported 37 sinkholes on primary roads and 116 on secondary so far in 2025, with repairs underway and projects including a new 2‑kilometer collector in Iztapalapa (about 50 million pesos) and ongoing fixes on Calzada Ignacio Zaragoza.