Overview
- Officials said on Sept. 23 that the federal plan will build 2,400 kilometers of passenger and linked freight lines with about 750 billion pesos in funding during the current sexenio.
- The government reports 787 km are under construction and 810 km are scheduled to start, with corridor completion ranging from roughly 10% to 45%—Mexico–Pachuca at about 45% and Mexico–Querétaro near 31%.
- Authorities aim to open parts of the AIFA–Pachuca and Mexico–Querétaro corridors in 2027 and have already received the first AIFA–Pachuca rail wagon at the Port of Manzanillo.
- The program is projected to serve some 41.3 million people, carry an estimated 220,000 passengers daily, cut average travel times by about 40% and avoid roughly 360,000 tonnes of CO2 per year, according to government figures.
- Delivery risks include finishing engineering and station designs, securing right-of-way and community agreements, completing procurement and rolling-stock deliveries, and publishing robust cost‑benefit and ridership evidence to validate the large investment.