Overview
- Provincial and national officials inspected Stage IV works, which will extend the Metrotranvía to El Plumerillo and are reported above 70% progress in multiple segments.
- Nearly 7.2 km of double track are installed between Godoy Cruz and Luján de Cuyo at 71% execution, with 3.7 km laid in Las Heras and energization and substation installations underway.
- Groundworks have begun for the airport connector, and the provincial plan targets completing the expanded network between September and October 2026.
- Rolling stock deliveries have reached 27 of 39 planned train sets after the last three arrived in November, and authorities are evaluating purchases of new units to meet expected demand.
- Aeropuertos Argentina plans terminal renovations beginning in July 2026 with completion estimated for October 2027, including expanded domestic and international boarding areas and a new VIP lounge.