  • AYSAM finished the planned works around 7 p.m. local time after a 4 a.m. start, moving into reservoir recovery and network purging.
  • Service will return progressively with full normalization in up to 24–48 hours as storage levels and pressure are restored.
  • The intervention commissioned the La Puntilla distribution and regulation chamber and large regulation valves to better route water from Luján I and Potrerillos toward Alto Godoy and Alto Benegas.
  • The outage covered wide areas of Gran Mendoza, and AYSAM deployed three tanker trucks to supply hospitals, dialysis centers and clinics.