Overview
- The Maryland Transportation Authority Board approved the $38.6 million Demolition and Miscellaneous Marine Work contract to Joseph B. Fay Company on Thursday.
- Preliminary site work will begin in December with heavier mechanical demolition scheduled for January and February, and the project will avoid explosives in favor of an excavator on a barge and clamshell dredges.
- The contract covers removal and salvage of remaining three-span steel girder sections, demolition of eight marine piers and two land piers, removal of nine marine foundations to the mud line, and cleaning 96-inch pipe piles.
- Maryland split the rebuild into four contracts after failing to reach terms with Kiewit over sharply higher cost estimates, and the overwater ‘mega-contract’ worth billions is under review with a builder expected by summer 2027.
- Officials say the work will clear the river, allow foundation preparation and recycling of recovered material, and the MDTA has launched an online dashboard to show task-level progress toward a completion target near Dec. 31, 2030.